Cost of Delay Calculator
How to Use This Calculator
- 1
Enter the length and daily cost of the delay
Fill in Delay Duration (days) and Daily Cost of Delay ($). The calculator multiplies these values to estimate the total cost.
- 2
Enter the probability of impact
Set Probability of Delay Impact (%) to the estimated chance that the delay's cost will affect the project. The adjusted result is total cost multiplied by this probability.
- 3
Review both cost estimates
Compare Total Cost of Delay with Adjusted Cost of Delay. Project Value ($) is an available input, but the current calculation does not use it in either result.
Example Calculation
A project is delayed by 10 days, with an estimated $5,000 cost per day and an 80% probability that the delay affects the project. The entered $500,000 project value does not affect the calculation.
Project Value ($)
500,000
Delay Duration (days)
10
Daily Cost of Delay ($)
5,000
Probability of Delay Impact (%)
80
Results
Total Cost of Delay
$50,000.00
Adjusted Cost of Delay
$40,000.00
Insights card shows the probability-adjusted exposure alongside the unadjusted delay cost.
Tips
Each additional delay day adds $5,000 before probability adjustment
Change Delay Duration (days) from 10 to 12 while keeping Daily Cost of Delay ($) at $5,000. Total Cost of Delay rises by $10,000, and Adjusted Cost of Delay rises by $8,000 at an 80% probability.
A lower impact probability reduces expected exposure
Change Probability of Delay Impact (%) from 80% to 50%. With 10 days at $5,000 per day, Adjusted Cost of Delay falls from $40,000 to $25,000.
Project Value does not cap or scale the output
Change Project Value ($) while leaving the other inputs unchanged. The two cost results stay the same because Project Value is not included in the calculation.
What this calculator estimates
Cost of delay is the estimated financial impact of completing a project later than planned. This calculator multiplies delay days by a daily cost, then applies a probability to estimate expected exposure; it does not use Project Value ($) in its formula.
How the calculation works
Total cost of delay = Delay duration × Daily cost of delay
Adjusted cost of delay = Total cost of delay × Probability of delay impact
Convert the probability percentage to a decimal before multiplying. For example, 80% becomes 0.80.
For the example, the unadjusted cost is 10 × $5,000 = $50,000. The adjusted estimate is $50,000 × 0.80 = $40,000. The $500,000 project value does not change either calculation.
What drives the estimate
The daily cost should reflect the actual economic consequence of a day of delay. It could include lost margin, extra labor, financing expense, or penalties, but the estimate should not count the same cost in more than one category.
| Delay duration | Daily cost | Probability | Total cost | Adjusted cost |
|---|---|---|---|---|
| 10 days | $5,000 | 50% | $50,000 | $25,000 |
| 10 days | $5,000 | 80% | $50,000 | $40,000 |
| 12 days | $5,000 | 80% | $60,000 | $48,000 |
The probability-adjusted result is useful for comparing uncertain risks, but it can hide the size of the full loss if the impact occurs. Review both outputs when deciding whether to spend money to prevent a delay.
Make the estimate useful for a decision
Use a range of daily costs and probabilities when the inputs are uncertain. For example, calculate a low, central, and high exposure rather than treating one probability as certain. Also check whether the cost is linear: a delay may trigger a deadline penalty or missed launch window that makes the cost jump rather than increase by the same amount each day.
For a fuller project estimate, separate recurring operating expenses from one-time costs using the Operating Cost Calculator and compare delay exposure with the alternative use of the same funds using the Opportunity Cost Calculator. The SBA's business planning guidance can help identify operating assumptions to include in a plan.
When to use a different calculator
- Estimate borrowing cost to fund a project overrun → Cost of Credit Calculator
- Estimate a project's ongoing expenses → Operating Cost Calculator
- Compare a decision with its next-best alternative → Opportunity Cost Calculator
- Calculate the cost impact of inflation over time → Cost of Inflation Calculator
Frequently Asked Questions
What is the cost of delay?
Cost of delay is the financial loss or added expense associated with a project finishing later than planned. This calculator estimates it as the number of delay days multiplied by the entered daily cost.
How do I calculate probability-adjusted cost of delay?
1. Multiply Delay Duration (days) by Daily Cost of Delay ($). 2. Convert Probability of Delay Impact (%) to a decimal. 3. Multiply the total delay cost by that probability.
Does Project Value affect the result?
No, Project Value ($) is not used by the current calculation. The outputs depend only on Delay Duration (days), Daily Cost of Delay ($), and Probability of Delay Impact (%).
Is adjusted cost the same as the amount I will definitely lose?
No, adjusted cost is an expected-value estimate, not a guaranteed loss. It multiplies the full delay cost by one probability and does not model different outcomes, partial impacts, or recovery after the delay.
How should I estimate the daily cost of delay?
Add the costs that actually accrue each day, such as lost contribution margin, extra staffing, or contractual penalties, and avoid counting the same loss twice. The U.S. Bureau of Labor Statistics' Employment Cost Index can provide context for labor-cost changes, but it does not estimate your project's delay cost.